J
James
We have an situation where a resource has booked four
hours on a Friday and four hours on a Satuday, and the
time has also been approved. When this is viewed either
from within Project Professional or any view in PWA other
than Portfolio Analyzer this is what is shown, however
when this is viewed in Portfolio analyzer it shows as 5.5
on Friday and 2.5 on Saturday.
Our Standard Calendar has a five and a half hour working
day and Saturday is set as non-working time.
We have republished the project and re-run the OLAP cube
but still the same. Does anyone have and idea on why this
occurs and what can be done about it?
hours on a Friday and four hours on a Satuday, and the
time has also been approved. When this is viewed either
from within Project Professional or any view in PWA other
than Portfolio Analyzer this is what is shown, however
when this is viewed in Portfolio analyzer it shows as 5.5
on Friday and 2.5 on Saturday.
Our Standard Calendar has a five and a half hour working
day and Saturday is set as non-working time.
We have republished the project and re-run the OLAP cube
but still the same. Does anyone have and idea on why this
occurs and what can be done about it?