I have a project with a task that is supposed to take 200 hours. The catch
is that the task is supposed to take from November 3, until March 15 of 2004
(next year). It is a DBA support task (I guess that would be considered
maintenance). How do I schedule this so that Project shows the task as
taking the entire length of time needed (until March) but still show it as
taking only 200 hours.
Thanks