A
Aasif
Our users update time on a weekly basis, But they have to put the actuals on
each task on a day to day basis.
Most of them will click on the "update all" button once they update the
time.
This sends an Update information to the Project Manager for all the task
they where ever assigned, even the ones that were completed a year ago.
Is there some way of avoiding this other than using "Update selected row" in
the timesheet.
each task on a day to day basis.
Most of them will click on the "update all" button once they update the
time.
This sends an Update information to the Project Manager for all the task
they where ever assigned, even the ones that were completed a year ago.
Is there some way of avoiding this other than using "Update selected row" in
the timesheet.