Time units on Resource View

E

Earl Forrence

(continued previous entry for fat-fingering)


In resource view ...

PM responsible for a plan has display in seconds. When I
see view the plan, it is displayed in hours.

But in his task usage view, it is displayed in hours

And in his Tools / Options / Schedule -- "Work entered"
is for hours

============

So, can anyone tell me what he did, and how to get display
to show hours again?

Thanks ... Earl
 
D

Dale Howard [MVP]

Earl --

Open the project in question, then click Tools - Macro - Macros. Run the
Format Duration macro and covert the Duration to Hours. Hope this helps.
 
G

Guest

Thank you ... will give it a try
-----Original Message-----
Earl --

Open the project in question, then click Tools - Macro - Macros. Run the
Format Duration macro and covert the Duration to Hours. Hope this helps.







.
 