TroyS
I know you can publish timephased date to the database, however, i'm looking
for a way to run a report out of a mpp file that shows:
- Task Name
- Resource name Actual Work by Day
I can analyze data in excel, however, this only gives me values at the task
name level and does not include the resource names.
I can set this up in a task usage view looking at the right hand pane that
shows Actual Work over a timeline such as by Day, however, it's not easy to
format and print this out.
I've played with the custom reports (copy an existing one), but the date
filter is by Task Start Date/Finish. I want to be able to select a
timeframe, say the previous week, and print this info out.....
any ideas?
for a way to run a report out of a mpp file that shows:
- Task Name
- Resource name Actual Work by Day
I can analyze data in excel, however, this only gives me values at the task
name level and does not include the resource names.
I can set this up in a task usage view looking at the right hand pane that
shows Actual Work over a timeline such as by Day, however, it's not easy to
format and print this out.
I've played with the custom reports (copy an existing one), but the date
filter is by Task Start Date/Finish. I want to be able to select a
timeframe, say the previous week, and print this info out.....
any ideas?