I have been asked to produce short term plan in hours. Can be done but
timescale shows 1st hour as 0 then on up to 23 which is confusing for
non-user. Can I change this??
 
J

JulieS

Hi Sandy M,

You can change the labels for the timescale through Format>Timescale. In
Project 2002 and 2003 (sorry I don't have 2000 readily available to check
options there) you could set the Middle Tier to Days and the Bottom Tier to
hours with whatever labels you think would be easiest for your users to
understand.

Hope this helps. Let us know how you get along.

Julie
 
J

JulieS

Thanks John. I remembered some change had happened, but forgot it was the 2
tier to 3 tier.
Julie
 
J

John

JulieS said:
Hi Sandy M,

You can change the labels for the timescale through Format>Timescale. In
Project 2002 and 2003 (sorry I don't have 2000 readily available to check
options there) you could set the Middle Tier to Days and the Bottom Tier to
hours with whatever labels you think would be easiest for your users to
understand.

Hope this helps. Let us know how you get along.

Julie
?

Julie,
Project 2000 works the same way except there are only two tiers.

John
 
S

Sandy M

Thanks Julie, that's sorted it, should have seen it myself but as usual
customer wants it immediately! Thanks a lot
Sandy
 
J

JulieS

Hi Sandy,
Glad to have helped and thanks for the feedback. Let us know if we can
assist again.
Julie
 