Timescale

S

Summer

I want to show "week ending" dates on my Gannt chart timescale instead of
"week starting". Is this possible?
 
J

JulieS

Hi Summer,

Sorry, to the best of my knowledge, no. Project by default shows week
starting data, not week ending data.

I hope this helps. Let us know how you get along.

Julie
 
J

JulieS

You're welcome Summer and thanks for the feedback. Sorry I couldn't give you
a "magic" fix you had overlooked as you hadn't overlooked anything.

Julie
 
R

Rene

Hi Summer;
It is possible to make this change. Double click on the Gantt Bar you
wish to change. Select the "Text" tab. The default for bars is
"Start". Use the pull-down menu to select "Finish". That will do it.

Rene
 