I wish to produce a project plan for a tool change
activity for which the duration of the tasks is in
seconds.

Is it possible to work in seconds on MS Project 2002 or is
minutes the closest I can get?.
 
M

Mike Glen

Hi Ray,

The answer is : no. If the whole project is short enough, you could treat
one minute to be one second.

In the future, try posting this on the project newsgroup, as this one is
closing down! Please see FAQ Item: 24. Project Newsgroups. FAQs,
companion products and other useful Project information can be seen at this
web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 