Brent:
Without selecting the setting Dale mentioned in his first reply:
2. Select the "Hours of work done per time period" option
The system is behaving as designed.
Brent99Admin said:
Thanks for the words of advice Dale on getting the environment solidified
prior to even the first project being published. To answer your question,
the setting in Project Server is set to 'Actual word done and work
remaining'. This is selected because we want resources to enter both
Actuals and ETCs for each of the tasks for which they have been assigned.
The actual setting in the project plan was never changed from the default
setting of 'Use the default method set on Project Server'. Therefore I
would have expected that the Timesheet page in PS would have allowed the
entry of both actuals on the right side of the grid and the ETC on the left
side of the grid.
With all of that being said when I have the 'Actual work done and work
remaining' option selected in PS, and based on your previous instructions
[which were exactly correct], I can enter in hours in the timesheet.
However as soon as I change the option in Project to match Project Server
2003 [Actual work done and work remaining], actuals cannot be entered into
the timesheet again. What am I missing? I'm also still unclear on why
using 'Use the default....' setting in Tools-->Customize-->Published Fields
in Project Professional does not honor the setting in Project Server. I'm
not trying to be difficult but I would appreciate further explanation...if
you have time.