Timesheet and My Tasks out-of-sync

M

Michael Brown

We may have stumbled upon a potential problem (issue? bug??) in 2007. A plan
is published along with assignments. A resource constructs his/her
timesheet. Prior to submission or task update, the plan changes (project
manager removes a particular task/assignment). Because the timesheet was
created at a moment in time, and is not PHYSICALLY tied to the plan through
primary/foreign key cascanding relationships, when the resource attempts to
import their timesheet data and submit it, they can run into a problem
because the task and associated time no longer exists in the plan. Anyone
else come across this one????
 
D

Dale Howard [MVP]

Michael --

Way back when we first started writing our Project Server 2007 book for
project managers, I learned the hard way that the list of tasks on the My
Timesheet page are "static and not automatic." By this I mean that if the
PM adds a new task in a project plan that occurs during the current My
Timesheet period, the new task does not automatically appear on the
timesheet. And if the PM deletes a task from the project plan the task is
not removed automatically from the timesheet.

Technically, this is not a bug, but rather, a serious design flaw. So, yes,
I have definitely run across this and we document this in our book. By the
way, if you don't have this book, it is avaiable at Amazom or at:

http://www.projectserverbooks.com

Hope this helps.
 
M

Michael Brown

Design flaw? Undocumented feature? Bug? Hm..... :))) definate room for
improvement! Thanks for the Information, dale. Looking forward to meeting
you soon I hope!
 
D

Dale Howard [MVP]

Michael --

Yup, there's LOTS of room for improvement! :) I will be at the Project
Conference in October. Stop by our msProjectExperts book and say Hi.
 