Timesheet approval-split resources

M

macs

I have a situation where in 1 project, there are multiple resource managers
that must approve the time for different resources. As the PM, I need to see
them, but not necessarily approve them all. How can I make this happen? I
have tried to re-publish the assignments just for those resources, and am not
having any luck. Is it a permissions issue?

Also as part of that same item, where I click "become manager of the
assignments", can I make different managers "approver" managers for those
resources? Thanks
 
M

Marc Soester [MVP]

Hi macs,

I assume you are using PS2003.
This is from memory :) havent worked with 03 for a while now :), but I
believe when you assign yourself as a project manager in Project Pro, you can
decide which tasks you want to manage. these task will then come to you for
approval when a resource entered task information.

Hope this helps
Marc
 
M

macs

Yes, but is there a way for me to assign the other RM's specific tasks or do
they need to open Pro and select their tasks to manage as well? Thanks.
 