Timesheet Dates Problem

  • Thread starter Ashish kanoongo
  • Start date
A

Ashish kanoongo

Hello

I did following settings in server setting - timesheet periods.
No of periods to be created - 52
Date the first periods start 1/1/2007
Type the standard period - 7

Now when ever I create bulk, it generates dates like
1/1/2007 - 1/5/2007
1/6/2007 - 1/10/2007
and so on

If you see january 2007 calendar, dates should be
1/1/2007 - 1/5/2007
1/8/2007 - 1/12/2007
and so on

I have alreayd set non working days as Sat-Sub, thne why it is not
considering in timesheet date generation.

Please let me know whats wrong I am doing?

Ashish
 
M

Mike Glen

Hi Ashish ,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

Ashish --

You created the Timesheet Periods incorrectly. You should have started the
first period beginning on December 31, 2006. The only way to rectify this
issue is to delete each of the Timesheet Periods and then recreate them.
That is why we recommend that you only create a few Timesheet Periods
initially using the bulk creation feature, since if you mess up the process,
you cannot do a "bulk delete." Also, the Saturday and Sunday non-working
times have nothing to do with Timesheet Periods. In the real world, people
do work on a Saturday or Sunday, and are included in the My Timesheet page
as a result.

Hope this helps.
 