Timesheet entries

D

David

If PM wants to accept/reject timesheet enteries sent by
consultants on a weekly basis. How can the PM
accept/reject individual days timesheet for the week as he
views the timesheet for the full week and is forced to
accept/reject for the full week tasks. Any suggestions?
Regards,
David.
 
G

Gary L. Chefetz

David:

You can only reject row-by-row (assignment-by-assignment); not day-by-day
entries.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 
D

David

What approach to take if the PM notices that for a
particular day during the week the consultant has entered
extra(wrong) time in the actual hours for the assignment.
Should the PM reject the assignment for the whole week?
Any ideas would be appreciated how to sort this issue?
Regards,
David.
 
G

Gary L. Chefetz

David:

It depends on how you're using the system. Again, when you reject an update,
it applies to the entire row. If there's one day of reporting in that row,
one day gets rejected. If there are two weeks of data in the row, then two
weeks gets rejected, and so on.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"