Timesheet entry for Team Leads

J

Jim Stoaks

I have a group that the manager wants the team leads to enter the % complete
for their teams through Web Access rather than having the team members do it.
The only way I can see doing it is to have the Leads logon as each team
member separately and then do the updates. Is there a way to enable leads to
see and update tasks their team members have responsibility for.

Thanks,
Jim
 
M

Marc Soester

Hi Jim,

PWA has a functionality called "Adjust Actuals" which can be found within
the Resource tab. Given that your Team leads have sufficient rights, they
should be able to update the timesheet for their resource.

All they need to to is
- go to the resource tab
- choose adjust actual within the action bar
- choose the resource under the "add/remove resource" link within the
customisation tabs
- update the tasks
- click on the "update actual" link. The PM will now be notified to approve
the project update.

I hope this helps
 