J
James
Hi,
We don't want resources to post hours over and above the original hours
scheduled for an assignment. In otherwords when a resource completes their
timesheet, once the remaning hours drop to zero and the task is marked as
complete, how do we stop resources booking additional hours to the task ?
Also we noticed that if someone makes a mistake, that is they enter 5h for a
task on a Tuesday in error, and that causes the task to be 100% complete if
they then go back and mark the 5h as 0h, it changes the remaining work value
to 5h,(and the work complete drops from 100% to 50%), when in fact it isn't.
Why does this behaviour occur and how do we prevent it from happening ?
Thanks
James
We don't want resources to post hours over and above the original hours
scheduled for an assignment. In otherwords when a resource completes their
timesheet, once the remaning hours drop to zero and the task is marked as
complete, how do we stop resources booking additional hours to the task ?
Also we noticed that if someone makes a mistake, that is they enter 5h for a
task on a Tuesday in error, and that causes the task to be 100% complete if
they then go back and mark the 5h as 0h, it changes the remaining work value
to 5h,(and the work complete drops from 100% to 50%), when in fact it isn't.
Why does this behaviour occur and how do we prevent it from happening ?
Thanks
James