J
José M. Dominguez
Hello:
I have some questions regarding the timesheet
functionality that are critical for a succesful
implementation of the EPM solution.
I want to avoid people on my organization tracking hours
on weekends and non working days, since this is not done
automatically by project web access depending on project
proffesional calendars, the only option I have is creating
managed periods, open periods for labour days and closed
periods for weekends. Then I was surprised to see that
resources were getting a message on their homepage saying
their timesheet was not sent on those weekend periods (for
which they don't have any hour planned).
First of all I would like to know in which case does
project server thinks the timesheet wasn't submitted. I
may have tasks planned for a managed period in which I
haven't been able to work because I've been working in
other tasks, and that doesn't mean that I haven't sent my
timesheet. (Do they have to insert zeros on such tasks?)
And then, is there a way of avoiding this message to
appear in the homepage. I don't want it to be displayed in
any case (I know it can be removed by cleaning the
projectserver database.
Thanks
José
I have some questions regarding the timesheet
functionality that are critical for a succesful
implementation of the EPM solution.
I want to avoid people on my organization tracking hours
on weekends and non working days, since this is not done
automatically by project web access depending on project
proffesional calendars, the only option I have is creating
managed periods, open periods for labour days and closed
periods for weekends. Then I was surprised to see that
resources were getting a message on their homepage saying
their timesheet was not sent on those weekend periods (for
which they don't have any hour planned).
First of all I would like to know in which case does
project server thinks the timesheet wasn't submitted. I
may have tasks planned for a managed period in which I
haven't been able to work because I've been working in
other tasks, and that doesn't mean that I haven't sent my
timesheet. (Do they have to insert zeros on such tasks?)
And then, is there a way of avoiding this message to
appear in the homepage. I don't want it to be displayed in
any case (I know it can be removed by cleaning the
projectserver database.
Thanks
José