Hi again all

Im coming up against a problem where a manager has booked some time to a
task that is not due to start until feb28th - my understanding of the PWA
timesheet would be that it would bring the task start date forward as actuals
are being booked. This does not seem to be the case and in the timesheet
aprrovals summary it does not register the hours to this task as being for
this week - so even though the submitted timesheet says 37 hours, the one in
the summary only has 30 (with the 7 hours to the task brought forward missing)

This cant be the correct way for the timesheet to work surely ?

and advise greatly accepted

Cheers

Mat
 