Timesheet Modification

J

Jason Short

Hi,

Is it possible to add extra lines and/or columns to the timesheet within
PS2007?

Essentially I am looking to add two or three columns and one or two lines.
I'm not bothered if it can only be done one way and not the other but would
welcome your comments.

Thanks in advance
 
J

Jason Short

Please ignore this request for help. I have discovered how to add columns and
additional Admin Time lines.
 
P

PedroJose

Hi Jason,

Could you please explain how?? I have been able to add extra columns (not
lines, actually I want to get rid of the "Planned" line), but the data that
is entered is not saved (i.e. it disappears upon hitting the save or save and
submit buttons..)

My need is to add a task percent complete in the timesheet (PWA2007) that
the resource can enter based on their knowledge of task progress, and have
that data transferred to My Tasks upon importing the timesheet. have not
been able to do this...

Thanks

PJ
 
Top