J
Jean-Luc.chantry
Hello
Anyone have and idea about that timesheet problem :
- Task with 2 h work
- you enter 9 h as actual work in you timesheet (you make a mistake !)
- Work is recalculated to 9h , logical !
- you modify entering 2 h
- Work is still 9 h an remaining work is 7 h
No way to cancel or rolling back
(even if you don't save)
only way : enter 0 in remaining Work
Nota: same behavior for an achivied task on witch you enter actual work
Thanks
jean-Luc Chantry
Just a link
Anyone have and idea about that timesheet problem :
- Task with 2 h work
- you enter 9 h as actual work in you timesheet (you make a mistake !)
- Work is recalculated to 9h , logical !
- you modify entering 2 h
- Work is still 9 h an remaining work is 7 h
No way to cancel or rolling back
(even if you don't save)
only way : enter 0 in remaining Work
Nota: same behavior for an achivied task on witch you enter actual work
Thanks
jean-Luc Chantry
Just a link