Timesheet : no second chance !

J

Jean-Luc.chantry

Hello

Anyone have and idea about that timesheet problem :

- Task with 2 h work
- you enter 9 h as actual work in you timesheet (you make a mistake !)
- Work is recalculated to 9h , logical !
- you modify entering 2 h
- Work is still 9 h an remaining work is 7 h

No way to cancel or rolling back
(even if you don't save)
only way : enter 0 in remaining Work

Nota: same behavior for an achivied task on witch you enter actual work

Thanks
jean-Luc Chantry
Just a link
 
K

Karl Kill, PMP

This is how it works. Same behavior in MS Project 2002 Pro Resource Usage sheet.

If no update, the project manager can reset the timesheet by republishing this task

Hope this helps.
 