Bill said:
Terry,
On the admin screen for the "Customize Web Access" The first opion on the
page "Specify the default method for reporting progress on tasks" lets you
set the percent complete option. Keep in mind this will be set system wide.
Bill
In Project Server 2003, there is no option to set "% Complete". It can
be argued that % complete is not a valid measure, since it measures
duration and not effort.
The options are:
Specify the default method for reporting progress on tasks
Percent of work complete: Resources report the percent of work
complete, between 0 and 100%.
Actual work done and work remaining: Resources report the actual
work done and the work remaining to be done on each task.
Hours of work done per day or per week: Resources report the hours
worked on each task during each time period.
Mark