J
Jonathan H
Hi,
I've just installed MS Project Server 2007 for the first time and as you
might expect I'm finding some of the changes from 2003 a little bewildering.
I'm slowly working through them, but the thing that has got me at the moment
is timesheets and tasks.
First question: How do those filling in the timesheets indicate the
remaining work left on a task?
Second question: Can anyone point me at a resource where I can see what the
interactions are between Tasks and Timesheets? Getting a room full of
developers to fill in Timesheets was hard enough in 2003, and on the face of
it it appears to have just got more complicated...
Thank you very much for any help. As I learn more, I'll try and post some
replies myself.
Jonathan
I've just installed MS Project Server 2007 for the first time and as you
might expect I'm finding some of the changes from 2003 a little bewildering.
I'm slowly working through them, but the thing that has got me at the moment
is timesheets and tasks.
First question: How do those filling in the timesheets indicate the
remaining work left on a task?
Second question: Can anyone point me at a resource where I can see what the
interactions are between Tasks and Timesheets? Getting a room full of
developers to fill in Timesheets was hard enough in 2003, and on the face of
it it appears to have just got more complicated...
Thank you very much for any help. As I learn more, I'll try and post some
replies myself.
Jonathan