Timesheet - reporting time as a percentage

K

Kristi

Is it possible to enter time as a percentage (instead of hourly) in Project
Server 2007 timesheets?

Kristi
 
D

Dale Howard [MVP]

Kristi --

As a percentage of what? Time is measured in units such as Hours or Days,
right? If you mean percentage of a task completed, your team members should
use the My Tasks page for this purpose. Let us know more about what you
mean.
 
K

Kristi

For my company, vendors in the U.S. are required to enter their project
efforts as a percentage. Since Vendor’s are invoiced based on a contract,
our legal department has expressed that it is not appropriate for us to
capture actual hours worked for a vendor.

So, we would like to use timesheets to track ACTUAL time for vendors as a
percentage of their project efforts. Is this possible? Thanks!

Kristi
 
D

Dale Howard [MVP]

Kristi --

The My Timesheet page is used to collect hours worked. Therefore, you
cannot capture the time of vendors as a percentage on a Timesheet. On the
other hand, you can enter a % Complete on the My Tasks page. Why don't you
require that instead? Hope this helps.
 