Timesheet Tasks?

  • Thread starter Shawn Everingham
  • Start date
S

Shawn Everingham

Looking at several resources in my project plan, utilizing the resource sheet
view, I see tasks that say My Timesheet as a task. 10hrs work and 10hrs
actual work. What is the deal with this? How do I get rid of those?

thanks!
 
D

Dale Howard [MVP]

Shawn --

I believe you are describing the default behavior of the Resource Usage
view, which is to show each project team member's work in other enterprise
projects and actuals from the Timesheet as well. If you do not want to see
this, do the following:

1. While in Microsoft Project 2007, click Tools - Enterprise Options -
Microsoft Office Project Server Accounts.
2. Select the "Manually control connection state" option.
3. Click the OK button.
4. Exit and relaunch Microsoft Project 2007.
5. In the Login dialog, deselect the "Load summary resource assignments"
option.
6. Click the OK button.

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top