Timesheet warning message

P

Paul Linscott

Several of our users receive the following message on their PWA home page:
"Your timesheet has not been submitted for the periods 3/28/2005 - 4/3/2005."

The users have entered and submitted time on mostly all the tasks during the
period of question and the PMs and administrator updated the project plans.
The tasks are from an administrative project and normal projects.

Also - we use the manage time period functionality as of 3/28. All periods
are closed outside of the current reporting period.

Under which condition/criteria will this message appear? I would think that
if a user enters even partial hours during a period, the system should flag
the timesheet as being updated for that period.

thx for your help

Paul
 
P

Paul Linscott

I forgot to add the manage period settings:

Our Tracking settings as follows:-

default method for reporting progress on tasks: Hours of work done per
day or per week
Lock down defaults: Force project managers to use the progress
reporting method specified above for all projects.
Time period settings: Managed Periods - Allow only Project Web
Access
users to update actual during open periods
Managed Timesheet periods: Resources should report their hours
worked every day

I read other threads on this subject. It seems that the only way to avoid
this message is to disable the manage period option. Maybe I'm wrong.
Hopefully help is on the way.

cheers

Paul
 
M

Mike Glen

Hi Paul,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top