Timesheet

C

cindy

We are in the process of implementing Professional,
Server, and PWA. Since team members will be entering
project time in PWA, we would like them to enter all non-
project time there also to simplify things for our payroll
timekeepers. We must capture cost data at the task level
so we designated one of the custom fields to contain the
cost codes. We have tried customizing views, reports,
etc. but can't seem to get all the data we need in one
view/report for the timekeepers. Can a report or view be
developed that will display all actual time worked in the
previous two-week period, by employee (not project), with
the data displayed for each task and cost code by day?
Thanks for the help.
 
G

Gary L. Chefetz \(MVP\)

Cindy:

This must be developed outside the interface as there's no way to create a
report like this using the tools provided under Manage views.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 