Timesheets don't allow edits of Flag fields

D

dbapmp

We display Flag1 for editing by our timesheet users. This was
editable in other projects' timesheets but is not editable in new
projects' timesheets. I cannot find any reference to why a flag would
be editable in one project and not editable in another.

Any ideas? Thanks in advance!
 
D

Dale Howard [MVP]

dbapmp --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is closing
down. To answer your question, assuming you are using Project Server 2003,
you must add the Flag1 field to the list of Published fields in EVERY
project. Click Tools - Customize - Published Fields, add the field to the
list on the right, and click the OK button. Then republish the assignments
using Collaborate - Publish - Republish Assignments. The last step
"unlocks" the Flag1 field for editing for all tasks in that particular
project. Hope this helps.
 