Hello...
I have 3 projects running on the server. One project does not allow
access to the daily hours panel on the right side of PWA screen. Can
you tell me what I'm doing wrong?
thanks
John
 
M

mark.everett

I am guessing that you don't have tracking options locked down and the
project manager of that project has chosed the % Work Complete method,
which uses the left side of the Task page.

But I am just guessing at that, since I don't know your environment.
That would be the first thing I checked.

Mark S. Everett | PMP
www.quantumpm.com
 
D

Dale Howard [MVP]

John --

Open the project in question and then click Tools - Customize - Publish
Fields. Select the "Hours of work per day or per week" option as the method
of tracking for this project and then click OK. Click Collaborate -
Publish - Republish Assignments and then click OK to "push" the new method
of tracking to each user's timesheet in PWA. Hope this helps.
 
J

jmac60

Thanks Dale..."publish fields" was properly set...needed to republish
assignments.