timeview

  • Thread starter Jan Paul Hoogendijk
  • Start date
J

Jan Paul Hoogendijk

Hi All,

i have had the following request:

Can you add a new field in the timesheet view (webaccess)
that makes it possible for teamleads to enter a ETC
(estimate to complete). This in regard of supporting the
project manager with adjusting his planning.

Pls mail replies to

[email protected]

Thanks
 
K

Kevin Flanagan

Actually every resource has the capability of entering
time worked and an entry for remaining work(ETC) as long
as your tracking settings are set: Hours of Work Done per
Day; Force Proj Mgrs...; Weekly; No. of Weeks (we use 2);
Resources should report their hours worked every day

Kevin
 
Top