I want to know what's effect of task prioriy on project and what priority is
high 0 or 500 and more then 500

regards

basim alvi
 
J

JackD

Priority is only used in leveling the project. If you are leveling then
priority is one of the possible fields which will determine the order in
which tasks get delayed. Priority of 1000 keeps a task from being leveled.
Other than that, you are free to use it to help you sort, group or filter
the project.
 