I've got some confusing because TOTAL ACTUAL WORK values for certain
projects did not same between the OLAP Cube (table MSP-CUBE_ASSN_FACT or
Portfolio Analyzer page) with Projects Center/ ms Project Pro (table
MSP_WEB_WORK or MSP_ASSIGNMENTS or MSP_WEB_ASSIGNMENTS).

Total Actual work values in the OLAP is less than total in the Projects
Center or actual work in the ms project professional.

I already built the CUBE again but the result still same.
 