Total Resources Overallocation

P

PK

Hello,

In Project 2002 I have several resouces in a group called "Inspection
Methods." Each resource in the group has an overallocation level,
however I would like to set an overallocation level for the group
itself. Can someone tell me if this is possible to track? Even if
there are unused Inspection Method resources I'd like at any given
time to limit scheduling within this group to three inspection
methods. Thanks in advance for advice.
 