Track actual work vs. baseline

Y

Yohann

Hello,

First sorry if I ask for something that has already been answered. I did not
find this information anywhere. We currently have our project managers
checking manually actual work logged by team members vs. estimates
(baseline). We would like to set up an automatic email reminder that would be
sent to the project manager when 80%, 90% and 100% of the baseline has been
reached with actual work. I only find auto-emails to be sent when a new task
is added/starts/ends/is overdue.
Are there auto-emails to flag cost issues?
 
D

Dale Howard [MVP]

Yohann --

No, the auto-emails you seek are not available in Project Server. To create
this would require custom software development. Hope this helps.
 
Y

Yohann

Thanks. That confirms what I was thinking on this matter. Maybe a feature of
Project Server 2007?
--
Yohann Charlet
Project Manager - MentorMate
http://mentormate.com


Dale Howard said:
Yohann --

No, the auto-emails you seek are not available in Project Server. To create
this would require custom software development. Hope this helps.
 
J

John Sitka

A scheduled MSSQL job works very well for this tiype of thing, ask your database developers or borrow one.