Track Project History

C

Cecile

Is there any way to track project history (old start dates) after multiple
baselines have been saved in Project 2002?

Thanks.
 
D

Dale Howard [MVP]

Cecile --

When the need for rebaselining occurs, you have a couple of options to track
Start dates at that point:

1. Save the Start, Finish, Duration, Work, and Cost information in
Baseline1-10 fields
2. Save the Start and Finish date information only in the Interim plan
fields (Start1/Finish1 - Start10/Finish10)

You would perform one of the above before rebaselining your project. Hope
this helps.
 
Top