Is there any way to customize the progress method in the timesheet entry
view by project. (ie) Project A tracks by % Complete, but project B tracks
by Actual work done and work remaining. From what I understand, this may be
done by changing the tracking method in PWA then have the owners of the
project (re) publish the project, and it would have to be done for each
project. This could cause a problem where project owner 1 is tracking by %
complete and re-publishes while the tracking method is set to Actuals
Worked.
Thanks
Marc Daoust
view by project. (ie) Project A tracks by % Complete, but project B tracks
by Actual work done and work remaining. From what I understand, this may be
done by changing the tracking method in PWA then have the owners of the
project (re) publish the project, and it would have to be done for each
project. This could cause a problem where project owner 1 is tracking by %
complete and re-publishes while the tracking method is set to Actuals
Worked.
Thanks
Marc Daoust