T
T
This is a typical scenario:
One task is set to take 2 hours on 10/3/03
But what if the task actually took 1 hour and started 10/4/03 instead? Once
I enter 1 hour, everything will adjust accordingly. This is very annoying:
It will say 50% completed since its basing of the 2h is was supposed to
take, and it says remaning is 1h.
This is particulary annoying in the PWA where it doesn't allow me to change
anything but % completed and remaning, and no matter what I change the
values are all dependent on each other. THis never allows me to enter a
different start date as well as more/less time than it was initially set to.
Help.
Any input is appreciated.
Thanks
One task is set to take 2 hours on 10/3/03
But what if the task actually took 1 hour and started 10/4/03 instead? Once
I enter 1 hour, everything will adjust accordingly. This is very annoying:
It will say 50% completed since its basing of the 2h is was supposed to
take, and it says remaning is 1h.
This is particulary annoying in the PWA where it doesn't allow me to change
anything but % completed and remaning, and no matter what I change the
values are all dependent on each other. THis never allows me to enter a
different start date as well as more/less time than it was initially set to.
Help.
Any input is appreciated.
Thanks