Tracking Gantt Chart

J

John

From what baseline does the tracking gantt chart come from? I know there
are multiple baselines that can be saved, but what baseline does the
tracking gantt chart use? And can that be changed? For instance, if I save
a baseline at the start of a project, then need to re-base using baseline1,
how can I get the tracking gantt chart to use baseline1 (or any of the other
baselines)?

Thanks
John
 
D

Dale Howard

John --

The default Tracking Gantt view uses the Baseline fields. If you wish, you
could make a copy of the Tracking Gantt view and then modify your custom
Tracking Gantt view to use any of the Baseline1 through Baseline10 fields
you choose. To actually modify it, double-click anywhere in the white of
the Tracking Gantt chart. In the From and To columns in the Bar Styles
dialog box, select the fields for the Baseline you wish to use. Hope this
helps.
 
J

John

Absolutely what I'm looking for. Thanks!!

Dale Howard said:
John --

The default Tracking Gantt view uses the Baseline fields. If you wish, you
could make a copy of the Tracking Gantt view and then modify your custom
Tracking Gantt view to use any of the Baseline1 through Baseline10 fields
you choose. To actually modify it, double-click anywhere in the white of
the Tracking Gantt chart. In the From and To columns in the Bar Styles
dialog box, select the fields for the Baseline you wish to use. Hope this
helps.
 