Hello Everyone!!
I have a resource working on three different tasks – Task A, Task B, Task C
simultaneously with unit contribution of 25%, 25% and 50% respectively. All
tasks start together and end together.
Task Start Finish Unit % Duration Work
Task A 3/23/05 5/30/05 25 52 d 98 h
Task B 3/23/05 5/30/05 25 52 d 98 h
Task c 3/23/05 5/30/05 50 52 d 196 h
When I view this schedule in a ‘Tracking Gantt’ view, Task C shows critical
even though the task status shows ‘On Schedule’. I am not really sure that
why a task which is on schedule be a critical one. Can somebody think of what
might have gone wrong? Please suggest me. Thanks a lot in advance. I
appreciate your help.
KT
PS: I have two more questions likely related to this tracking Gantt. I will
post them separately.
I have a resource working on three different tasks – Task A, Task B, Task C
simultaneously with unit contribution of 25%, 25% and 50% respectively. All
tasks start together and end together.
Task Start Finish Unit % Duration Work
Task A 3/23/05 5/30/05 25 52 d 98 h
Task B 3/23/05 5/30/05 25 52 d 98 h
Task c 3/23/05 5/30/05 50 52 d 196 h
When I view this schedule in a ‘Tracking Gantt’ view, Task C shows critical
even though the task status shows ‘On Schedule’. I am not really sure that
why a task which is on schedule be a critical one. Can somebody think of what
might have gone wrong? Please suggest me. Thanks a lot in advance. I
appreciate your help.