Tracking Gantt View in Project Center

D

dave

In the Project Center view in PWA- Is it possible to view all project
summary tasks plus one addition outline level?

Example View

Project One
Deliverables
Project Two
Deliverables
Project Three
Deliverables

Dave
 
D

Dale Howard

Dave --

Project Center views are limited to a single line only for each project, and
cannot show any project detail below the project summary task. If you
really need to do what you have shown in the example, then you might create
a temporary master project in Microsoft Project 2002. Once created, you can
set the master project to show only the project summary task plus the first
outline level for each subproject. If you do this, take special care that
you do not attempt to publish from this master project. Hope this helps.
 
D

dave

Hi Dale

Thanks for the advice. It is unfortunate that PWA doesn't have a more
dynamic control of the gantt view. I was looking for a Server side
solution.

Thanks
Dave
 