Tracking Gantt

J

John

My supervisor wants to print a copy of the Tracking Gantt chart. We can do
that easily enough. However, for the summary tasks, Project puts a
percentage for the subtasks right on the summary task bar (thereby covering
up the summary task bar). It's only noticable from the print preview screen
or directly on paper. I want to stop the percentage covering from
happening. Anyone know how to do this?


Thanks
John
 
M

Mike Glen

Hi John,

Welcome to this Microsoft Project newsgroup :)

Well, you could format the bar styles and put the % at the end of the bars
(via the Text tab), or at one of the other orientations. You could also
widen the rows.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>
Please note the new Project newsgroup arrangements repeated in FAQ 24 -
Project Newsgroups, as this one is closing down.


Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 