D
dwolf
I am setting up an equipment test program in Project 2000 with
technicians, engineers, etc. I also wish to add the quantity of test
pieces required for each test. So far this is straight-forward... The
test pieces are entered as material and the technicians, etc are
entered as work.
The difficulty becomes when I am trying to determine the minimum number
of test pieces I can use to complete the test program. Resource Usage
will keep track of the total test pieces based on no common test pieces
between tests. The right-hand pane insists on distributing the
quantity over time. So a requirement for 5 test pieces on a 5-week
test will show as 1 unit per week. Changing the "Accrue At" to Start
does nothing to solve the problem.
Is there an easy way around this that I am missing? Or do I need to
copy the time-phased data into Excel to sum the quantities up? I can't
use 2-1/3 test units as an answer.
Hopefully someone has an elegant solution....
Thanks,
--dwolf
technicians, engineers, etc. I also wish to add the quantity of test
pieces required for each test. So far this is straight-forward... The
test pieces are entered as material and the technicians, etc are
entered as work.
The difficulty becomes when I am trying to determine the minimum number
of test pieces I can use to complete the test program. Resource Usage
will keep track of the total test pieces based on no common test pieces
between tests. The right-hand pane insists on distributing the
quantity over time. So a requirement for 5 test pieces on a 5-week
test will show as 1 unit per week. Changing the "Accrue At" to Start
does nothing to solve the problem.
Is there an easy way around this that I am missing? Or do I need to
copy the time-phased data into Excel to sum the quantities up? I can't
use 2-1/3 test units as an answer.
Hopefully someone has an elegant solution....
Thanks,
--dwolf