M
Martin
Hi,
I'm new to Project 2003 and wonder if it would be a good choice to track
servers for the life of the server, and budget for upcoming fees and
replacement costs. As a simple example, I'm imagining a 24-hour Calendar and
Gantt chart with finish-to-start tasks something like this:
1. Spec and order server (1 week)
2. Build, test and put in production (2 weeks)
3. Server in production (3 years)
4. Retire server (1 week)
This basic sequence of tasks would be repeated for each server. Then for my
budgeting needs, some tasks would have costs. For example, 1. would have the
inital purchase price, and 3. would have recurring sub-tasks with annual
costs for software maintenance, license fees, etc. Near the end of 3 years,
I would add another set of tasks to budget for server replacement, and the
life-cycle would repeat. Besides the Gantt chart, I found the 'Task Usage'
view which looks like it can be configured to show Cost, so I can see future
budget requirements.
I've searched for pre-configured templates, and newsgroup discussions on
this topic, but so far have been unsuccessful. The Microsoft 'Infrastructure
Deployment Template' looked promising, but appears to be designed for setting
up a datacenter, not for on-going server life-cycle management.
What do you think? Is Project overkill, unsuited, just right? Should I
consider other Project features? Should I change my concept to work more
effectively with Project?
Thanks,
- Martin
I'm new to Project 2003 and wonder if it would be a good choice to track
servers for the life of the server, and budget for upcoming fees and
replacement costs. As a simple example, I'm imagining a 24-hour Calendar and
Gantt chart with finish-to-start tasks something like this:
1. Spec and order server (1 week)
2. Build, test and put in production (2 weeks)
3. Server in production (3 years)
4. Retire server (1 week)
This basic sequence of tasks would be repeated for each server. Then for my
budgeting needs, some tasks would have costs. For example, 1. would have the
inital purchase price, and 3. would have recurring sub-tasks with annual
costs for software maintenance, license fees, etc. Near the end of 3 years,
I would add another set of tasks to budget for server replacement, and the
life-cycle would repeat. Besides the Gantt chart, I found the 'Task Usage'
view which looks like it can be configured to show Cost, so I can see future
budget requirements.
I've searched for pre-configured templates, and newsgroup discussions on
this topic, but so far have been unsuccessful. The Microsoft 'Infrastructure
Deployment Template' looked promising, but appears to be designed for setting
up a datacenter, not for on-going server life-cycle management.
What do you think? Is Project overkill, unsuited, just right? Should I
consider other Project features? Should I change my concept to work more
effectively with Project?
Thanks,
- Martin