J
Jack Kohn
I'd like to poll the group and the experts about how to best handle
our need to track team members' non-project-related time.
When I say "non-project-related," I am referring to things like sick
time, vacation time, training time, jury duty, etc.
We, of course, need to plan for this time. We make the assumiption it
accounts for 20% off the top of schedules as overhead. We have done
that by setting our Standard enterprise calendar to 7 hrs/day and 35
hrs/week.
We would also like to track non-project-related time with some degree
of detail looking backwards. That is, we like to be able to track that
person X spent four-days at training; a development project fell
behind due to sick time, etc. Throwing it all in Project's non-project
time won't give us the granularity we want.
So, we have set up "General Administration" projects for each group
with tasks for each bucket of time to track. We have tasked the PMs
with inputting non-project-related time for their staff. (We are
currently piloting Project 2002 Pro and Server.)
Now comes our uncertainty: Initially, we thought we'd use the options
to import non-working time from Outlook, or have team members report
schedule changes/non-working time via PWA. But, if we're having
managers account for people's non-project-realted time in the General
Administration projects, won't adding non-working time to their
schedules cause "double-dipping" as far as a person's availability?
It seems like we should forget importing non-working time from
Outlook/PWA and just use tasks in the Gen Admin project.
By the way, the explanation on p.216-217 of Gary Chefetz's book gave
us some good insight that we might be making a mistake here (I think!)
and also gave us a clue about using "demand" resource assignments
here.
Also - we plan to move to Project 2003, which I hear will handle Gen
Admin tasks much better. How will our scenarios change in 2003?
Any advice? Thanks in advance.
-jmk
our need to track team members' non-project-related time.
When I say "non-project-related," I am referring to things like sick
time, vacation time, training time, jury duty, etc.
We, of course, need to plan for this time. We make the assumiption it
accounts for 20% off the top of schedules as overhead. We have done
that by setting our Standard enterprise calendar to 7 hrs/day and 35
hrs/week.
We would also like to track non-project-related time with some degree
of detail looking backwards. That is, we like to be able to track that
person X spent four-days at training; a development project fell
behind due to sick time, etc. Throwing it all in Project's non-project
time won't give us the granularity we want.
So, we have set up "General Administration" projects for each group
with tasks for each bucket of time to track. We have tasked the PMs
with inputting non-project-related time for their staff. (We are
currently piloting Project 2002 Pro and Server.)
Now comes our uncertainty: Initially, we thought we'd use the options
to import non-working time from Outlook, or have team members report
schedule changes/non-working time via PWA. But, if we're having
managers account for people's non-project-realted time in the General
Administration projects, won't adding non-working time to their
schedules cause "double-dipping" as far as a person's availability?
It seems like we should forget importing non-working time from
Outlook/PWA and just use tasks in the Gen Admin project.
By the way, the explanation on p.216-217 of Gary Chefetz's book gave
us some good insight that we might be making a mistake here (I think!)
and also gave us a clue about using "demand" resource assignments
here.
Also - we plan to move to Project 2003, which I hear will handle Gen
Admin tasks much better. How will our scenarios change in 2003?
Any advice? Thanks in advance.
-jmk