Tracking Risks and Issues in MSProject

  • Thread starter Shiva Chaitanya
  • Start date
S

Shiva Chaitanya

Hi

Is there any option in MS Project where I can track risks and issues of a
project without interference of Sharepoint server?

Thank you
Shiva Chaitanya.
 
R

Rob Schneider

Not directly in the way I presume you are looking for.

Use Project to track the planned project deliverables associated with
working the issues and risk mitigations. Plans/assignments for working
issues and mitigating risks ought to be in the project plan (and budget!).

I find it strange calling "SharePoint an interference ... I consider
SharePoint a great resource. You could use SharePoint (outwith Project
Server and EPM) as a great place to keep the lists Risks and Issues to
help with the visibility.


--rms

www.rmschneider.com
 
J

Jim Aksel

I have a white paper on Risk Resgiter and cost impacts posted on my blog. Go
to the URL below and then click MS Project Tips.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 