Tracking Settings in PWA no reflecting correct choice

T

T

Dear Group,

I am trying out project server and Project Pro. I am Running into the
following problem. The admin accounts has forces a certain tracking method
(actual hours worked and remaining hours). A project manager creates the
plan, saves the baseline and starts tracking by publishing the tasks to all
users, selects tracking method (fixed due to administrator settings), saves
and exits.

Now when the team member logs in and goes to tasks, the tracking method is %
completed and hours remaning. This is not the choice I have selected. No
matter what I try the team member never is able to edit actual
hours/remaning hours. Also, there is no ability to enter actual start date
if the task actually was started on a different start date than scheduled.

I am testing out Pro 2003 and Server 2003.

Any input is appreciated.

Thanks
 
Top