transfer formatting between projects

  • Thread starter transfer formatting between projects
  • Start date
T

transfer formatting between projects

Hello! I would like to copy data from a project into another. However the
formatting are lost in the columns. I try to transmit the data over the task
object in a For each instruction. With FormatCopy or FormatPaint it does not
go... as can I formatting (fat, italic, color) from the active cell pick out
and to the new project transfer?
 
R

Rod Gill

Hi,

Formatting is stored in the Views. In your original Project select tools,
organizer

Rename the View in your original project
Copy it to the Global.Mpt file

Now it's available in all projects you open.

--

Rod Gill
Project MVP