M
Michael Gwin
I have a program plan where I list multiple projects that all have the same
subtasks (milestones for those projects). I want to be able to list the
individual tasks out in a report, per project, instead of projects, per task.
For Example...
Program
Project1
Milestone1
Milestone2
Milestone3
Project2
Milestone1
Milestone2
Milestone3
etc
Id like to see a report showing the following:
Milestone1
Project1
Project2
Milestone2
Project1
Project2
If its not easy, Im thinking I will redo the plan but I have several hours
into it already and would rather not. I know I can filter by the Milestone
but then the output looks like:
Project1
Milestone1
Project 2
Milestone1
Project 3
Milestone1
Not ideal but I suppose functional if thats the way I have to do it. Im
trying to get a summary vew that I can put on a scorecard for my leadership.
Id like it to be as crisp as possible.
Thanks for the help.
Mike
subtasks (milestones for those projects). I want to be able to list the
individual tasks out in a report, per project, instead of projects, per task.
For Example...
Program
Project1
Milestone1
Milestone2
Milestone3
Project2
Milestone1
Milestone2
Milestone3
etc
Id like to see a report showing the following:
Milestone1
Project1
Project2
Milestone2
Project1
Project2
If its not easy, Im thinking I will redo the plan but I have several hours
into it already and would rather not. I know I can filter by the Milestone
but then the output looks like:
Project1
Milestone1
Project 2
Milestone1
Project 3
Milestone1
Not ideal but I suppose functional if thats the way I have to do it. Im
trying to get a summary vew that I can put on a scorecard for my leadership.
Id like it to be as crisp as possible.
Thanks for the help.
Mike