I have a resource loaded IMS that I am trying to copy into a project template
that was created for our citrix server environment and I can not get the
timephased work and baseline work to copy over correctly. Any suggestions?
 
S

Scott m Wagner - EPM Consulting Services

Newbee,

Can you provide some additional information? Is the resource loaded in the
Enterprise Resource Pool? You said you are trying to put the resource into a
project template, are you sure this is the approach you want or are you just
trying to create a new project plan based on an existing template?

How did you enter the resource? Did you look them up or just type the name
in the resource pool?

I may be able to help you more if you can provide this information.