I need to see a project delay for all projects in Project Center.
For this purpose I created a formula at project level that calculates
project delay.
When I open a single project in Pro, the value in Project Summary Task
is filled down for all tasks and that's right.
But all my single projects are also part of the Master Project. When I
open Master Project, all inserted projects receive the value of the
Master Project Summary Task that I really don't want to (in my case it
has no sense).
How can I "lock" the subprojects from changing values?
If anyone has experience working with Masters in MSP 2003?
Any help will be greatly appreciated,
Rimma.
For this purpose I created a formula at project level that calculates
project delay.
When I open a single project in Pro, the value in Project Summary Task
is filled down for all tasks and that's right.
But all my single projects are also part of the Master Project. When I
open Master Project, all inserted projects receive the value of the
Master Project Summary Task that I really don't want to (in my case it
has no sense).
How can I "lock" the subprojects from changing values?
If anyone has experience working with Masters in MSP 2003?
Any help will be greatly appreciated,
Rimma.