M
mikeh
I have two projects, and I’m not sure if I need to link them or if I should
combine them into a single project plan. (I don’t have any experience with
linking.) I’ve read a lot of posts, but would like to get everyone’s advice
here. I am using Project 2000; here is the scenario:
I have one large project, let’s call it “MainProj,†with 6 developers and 3
testers.
I also have a second concurrent project, let’s call it “SecondProj,†which
uses two of the above developers and one of the above testers.
Here is additional information:
1. For one of the SecondProj tasks, there is a dependency to a MainProj
task. (More precisely, this is a certain chunk of SecondProj development
that must wait until a certain chunk of MainProj development/testing is
completed.)
2. Since resources are shared, I will need to level resources across both
projects.
3. The project sponsors are different. I don’t want/need to show MainProj
progress to the SecondProj sponsors. I’ll only need to show SecondProj
status.
So for points 1 and 2, this would make me lean toward a single combined
project plan. However, point 3 makes me think I should keep them separate
and try to link.
What do you think? Thanks!
combine them into a single project plan. (I don’t have any experience with
linking.) I’ve read a lot of posts, but would like to get everyone’s advice
here. I am using Project 2000; here is the scenario:
I have one large project, let’s call it “MainProj,†with 6 developers and 3
testers.
I also have a second concurrent project, let’s call it “SecondProj,†which
uses two of the above developers and one of the above testers.
Here is additional information:
1. For one of the SecondProj tasks, there is a dependency to a MainProj
task. (More precisely, this is a certain chunk of SecondProj development
that must wait until a certain chunk of MainProj development/testing is
completed.)
2. Since resources are shared, I will need to level resources across both
projects.
3. The project sponsors are different. I don’t want/need to show MainProj
progress to the SecondProj sponsors. I’ll only need to show SecondProj
status.
So for points 1 and 2, this would make me lean toward a single combined
project plan. However, point 3 makes me think I should keep them separate
and try to link.
What do you think? Thanks!