T
TCO
I’m having problems resource leveling among linked projects using a resource
pool.
I have two projects and one resource pool. I linked several tasks from
project A to project B. I leveled project A and it worked fine. I then
leveled project B, at a lower priority and it is having the following effect.
Any resource working on both projects seems to be excluded from being
available to project B during the time frame the resource is being used for
project A. This is the case even if the resource is not fully allocated. So
in my case, the resources are allocated 10% of their time to a task on
project A. That means they should be available the remainder of their time
for tasks on project B. However, they are only being released to work on
project B once the task in project A is completely finished. They should be
able to work tasks in both projects at the same time.
After I leveled project A I set the priority for it to 1000 because I did
not want any of its activities to move while I leveled project B. I thought
this may be the problem but then I set the priority for project A to 900 and
tried leveling project B but the results were the same.
What am I doing wrong?
Thanks,
pool.
I have two projects and one resource pool. I linked several tasks from
project A to project B. I leveled project A and it worked fine. I then
leveled project B, at a lower priority and it is having the following effect.
Any resource working on both projects seems to be excluded from being
available to project B during the time frame the resource is being used for
project A. This is the case even if the resource is not fully allocated. So
in my case, the resources are allocated 10% of their time to a task on
project A. That means they should be available the remainder of their time
for tasks on project B. However, they are only being released to work on
project B once the task in project A is completely finished. They should be
able to work tasks in both projects at the same time.
After I leveled project A I set the priority for it to 1000 because I did
not want any of its activities to move while I leveled project B. I thought
this may be the problem but then I set the priority for project A to 900 and
tried leveling project B but the results were the same.
What am I doing wrong?
Thanks,